Phone: 425.415.0551

Fax: 425.415.0311

Email: info@riley-group.com


Riley Group Corporate Office

17522 Bothell Way NE

Bothell, WA 98011


© 2014 Riley Group.
All rights reserved.

Whitman College

Posted on

whitman

RGI conducted a Phase II subsurface soil and groundwater investigation at the Whitman College Physical Plant. The purpose of this Phase II was to evaluate soil and groundwater quality following the 1999 decommissioning (by removal) of two, approximately 4,000-gallon, diesel fuel, steel underground storage tanks (USTs). At least one of the USTs had leaked as evidenced by corrosion holes in the steel and the presence of free product in the UST cavity, although no groundwater quality investigation was performed.

Four groundwater monitoring wells were installed by RGI to evaluate groundwater quality with the goal of obtaining a determination of no further action (NFA) from the Washington State Department of Ecology.

RGI was contracted to conduct on-going groundwater monitoring through July 2014. In addition, RGI also conducted the UST site assessment for a decommissioned, closed-in-place concrete bunker oil UST.

Environmental services included:

  • Conducting a Phase II Subsurface Investigation
  • Environmental testing of the soil and groundwater
  • Preparing final report for the site, including wells for groundwater testing
  • On-going groundwater monitoring
  • UST site assessment